Stormwater Management

Alamance County Watershed Stormwater LimitsSome Restrictions

Alamance County limits impervious built-upon area to control stormwater runoff into the Back Creek, Stoney Creek, Big Alamance Creek, Cane Creek, Rocky River and Haw River water supply watersheds. UDO § 6.10 caps built-upon area at six percent of lot size in Watershed Critical Areas and twelve percent in the Balance of Watershed, with density held to one dwelling per two acres in critical areas and one dwelling per acre elsewhere.

Key Facts

WCA built-upon cap
6% of lot area
BOW built-upon cap
12% of lot area
WCA minimum lot
2 acres per dwelling
Lake buffer
100 feet from normal pool elevation
SNIA maximum
70% built-upon with Board approval
Enforcing office
Watershed Administrator, Administrative Services Dept

In order to maintain a predominantly undeveloped land use intensity pattern in the WCA, single-family residential, multi-family residential and non-residential development shall be allowed at a maximum of one dwelling unit or use per two acres (1 d.u. or use/2 ac.). Built-upon area for multi-family residential and non-residential development shall not exceed six percent (6%) of lot area except for expansion of existing development.

Full breakdown

The Watershed Protection Standards divide the county's public water supply watersheds into two zones: the Watershed Critical Area (WCA), covering land within one mile of a reservoir's normal pool elevation or upstream of an intake, and the Balance of Watershed (BOW), the remaining contributing drainage area. In the WCA, single-family lots cannot be smaller than two acres, and multi-family or non-residential development cannot exceed six percent built-upon area per project, calculated against total tract acreage. In the BOW, single-family lots must be at least one acre, multi-family and non-residential uses need forty-thousand square feet per unit, and built-upon area is capped at twelve percent.

Institutional non-residential uses in the BOW, such as churches, schools, fire stations and government buildings, can exceed the twelve percent cap through a Special Non-Residential Intensity Allocation (SNIA) approved by the Board of Commissioners on recommendation of the Planning Board, up to seventy percent built-upon area on an individual project, capped county-wide at ten percent of each watershed's balance acreage. A one-hundred-foot natural buffer must be maintained around every water supply reservoir measured from the normal pool elevation, with new development barred inside it except water-dependent structures and public road or greenway crossings.

Bona fide farms are exempt from the watershed density and built-upon limits under § 6.10.6, though they remain subject to other federal, state and local rules. The Watershed Administrator in the Administrative Services Department administers the program, adopted under N.C.G.S. § 160D-926 and Article 21 of Chapter 143 of the General Statutes.

Violations & penalties

Building, altering, or changing the use of property without securing a Watershed Protection Permit from the Watershed Administrator violates § 6.10.8, and no state building permit can be issued until that permit is granted. Occupying a structure before the county issues a Watershed Protection Occupancy Permit is likewise a violation; if occupancy is denied, the Administrator must notify the applicant in writing of the reasons. Exceeding the six or twelve percent built-upon area cap for a project violates the density standard in § 6.10.2 and § 6.10.3.

Stormwater Management FAQ

Does Alamance County limit how much of my lot can be paved or built on?
Yes. Inside the Watershed Critical Area the county caps built-upon area for multi-family and non-residential projects at six percent of lot size, and inside the Balance of Watershed the cap rises to twelve percent, under UDO § 6.10.2 and § 6.10.3. Single-family lots instead face minimum lot sizes of two acres in the critical area and one acre in the balance.
Which parts of the county are covered by the watershed rules?
The rules apply to the Back Creek, Stoney Creek, Big Alamance Creek, Cane Creek, Rocky River and Haw River drainage areas that feed the water supply reservoirs used by Burlington, Graham, Mebane and the Orange Water and Sewer Authority, as set out in UDO § 6.10.1.
Can a project exceed the built-upon area cap?
Only institutional non-residential uses such as churches, schools, fire stations and government buildings in the Balance of Watershed can exceed twelve percent, up to seventy percent on an individual project, through the Special Non-Residential Intensity Allocation approved by the Board of Commissioners under § 6.10.3(4).
Are farms subject to the watershed density limits?
No. Section 6.10.6 exempts bona fide farms from the watershed regulations, though farms still must follow other applicable federal, state and county rules, including any Soil Conservation Service conservation plan recommendations.

Sources & official references

Erosion Control

Alamance County Erosion and Sediment Control PlanSome Restrictions

Alamance County requires subdividers to submit an erosion and sediment control plan to the North Carolina Department of Environmental Quality before disturbing more than one acre of land, per UDO Section 6.9.5(C). The plan is one of the improvements the Planning Department must confirm before it grants final plat approval on any subdivision within the county's unincorporated jurisdiction.

Key Facts

Trigger threshold
Plans required above 1 acre disturbed
Approving agency
NC Dept. of Environmental Quality
Governing section
UDO Section 6.9.5(C)
Improvement guarantee
18 months, 125% surety bond
Civil penalty
$500 per violation, per day
Criminal penalty
Class III misdemeanor, up to $500

Erosion and Sediment Control Plans. Subdividers are required to submit erosion and sediment control plans for all land disturbing activities covering more than one (1) acre to the North Carolina Department of Environmental Quality.

Full breakdown

Section 6.9.5 of the Unified Development Ordinance lists the improvements a developer must install or guarantee before Alamance County grants final plat approval. Under 6.9.5(C), 'Within the Jurisdiction of this Ordinance,' subdividers doing any land-disturbing activity covering more than one acre must submit an erosion and sediment control plan and get it approved by the North Carolina Department of Environmental Quality before construction proceeds; the requirement sits alongside street clearing, grading, base and paving standards that must also meet N.C. DOT specifications. Where the land lies within the subdivision jurisdiction of a municipality that has adopted the ordinance by resolution, Section 6.9.5(B) instead sends the developer to that town's own improvement standards.

Once grading starts, Section 6.9.5(D) separately requires debris, fallen trees, and other obstructions to be cleared from stream channels and drainage ways before the county will sign off on the final plat. Developers of private-road subdivisions face a parallel duty under Appendix L: an erosion control plan for the road corridor is required whenever more than one acre is cleared. Instead of finishing every improvement before recording, Section 6.9.5(A) lets a subdivider guarantee the work with a surety bond, letter of credit, or equivalent instrument worth 125% of the construction cost, payable to Alamance County, and complete the work within eighteen months; an engineer registered in North Carolina must certify the construction and surety amounts. The Planning Department administers plat approval and can withhold it until the erosion and sediment control plan is on file.

Violations & penalties

Skipping the required plan or disturbing land without one violates Article 4 of the UDO. The Planning Director gives the responsible party 30 days to correct the violation before imposing penalties: a civil citation of $500 per violation, with each day of continued violation a separate offense, or criminal prosecution as a Class III misdemeanor under N.C.G.S. § 14-4 carrying a fine up to $500. Staff may also issue a stop-work order halting the land-disturbing activity immediately if it endangers life or property; violating that order is itself a Class 1 misdemeanor.

Erosion Control FAQ

Does every Alamance County subdivision need an erosion control plan?
Only if the land-disturbing activity covers more than one acre. Section 6.9.5(C) of the UDO requires subdividers above that threshold to submit an erosion and sediment control plan to the North Carolina Department of Environmental Quality before the county will count that work toward final plat approval. Smaller disturbances are not covered by this county requirement.
Who reviews and approves the erosion control plan?
The North Carolina Department of Environmental Quality, not the Alamance County Planning Department, reviews and approves the erosion and sediment control plan under Section 6.9.5(C). County staff confirm the approved plan is on file as one of the improvements required before they will grant final plat approval on the subdivision.
What happens if a developer disturbs land without an approved plan?
The Planning Director can issue a stop-work order halting the land-disturbing activity immediately, then allow 30 days to correct the violation under Article 4. Continued noncompliance draws a $500 civil citation per day or prosecution as a Class III misdemeanor carrying up to a $500 fine under N.C.G.S. § 14-4.

Sources & official references

Flood Zones

Alamance County Floodplain Development PermitSome Restrictions

Any development within a Special Flood Hazard Area in Alamance County, including its extraterritorial jurisdiction with the Village of Alamance, requires a Floodplain Development Permit from the Planning Director before work begins, backed by a certified plot plan, flood zone designation, and proposed elevations.

Key Facts

Permit required
Floodplain Development Permit before any work
Issuing authority
Planning Director as Floodplain Administrator
Coverage area
County plus Village of Alamance ETJ
Map revision deadline
Adopt LOMR/PMR within 3 months
Stop-work violation
Misdemeanor

This section applies to all Special Flood Hazard Areas within the jurisdiction of Alamance County, including Extra-Territorial Jurisdictions of the Village of Alamance. […] Application for a Floodplain Development Permit shall be made to the Planning Director, hereinafter referred to as the Floodplain Administrator, prior to any development activities located within Special Flood Hazard Areas.

Full breakdown

Section 6.4.1 of the Unified Development Ordinance applies the county's flood damage prevention rules to every Special Flood Hazard Area within Alamance County's jurisdiction, including the Extra-Territorial Jurisdiction it shares with the Village of Alamance. Those areas are the ones mapped under FEMA's Flood Insurance Study and Digital Flood Insurance Rate Map panels, adopted by reference into the ordinance; later Letters of Map Revision or Physical Map Revisions must be adopted within three months. Section 6.4.4 requires anyone proposing development in a mapped Special Flood Hazard Area to apply to the Planning Director, who serves as Floodplain Administrator, for a Floodplain Development Permit before any work starts.

The application must include a certified plot plan showing the nature, location, dimensions, and elevations of the proposed development; the Special Flood Hazard Area boundary; the flood zone designation; the floodway or non-encroachment area boundary; the Base Flood Elevation where one has been set; and any relocation of a watercourse. Applicants must also submit proposed elevation data, tied to NAVD 1988, for the reference level of every structure and, where floodproofing is used for a non-residential building, a FEMA Floodproofing Certificate (Form 086-0-34) with an operational and maintenance plan.

Once a permit issues, the Floodplain Administrator can make onsite inspections as work progresses, issue a stop-work order if construction violates the ordinance or the permit's terms, and revoke the permit for a substantial departure from the approved plans or for false statements made to obtain it. The Administrator also advises owners whose lowest floor sits above the BFE that they may apply to FEMA for a Letter of Map Amendment.

Violations & penalties

Developing in a Special Flood Hazard Area without a Floodplain Development Permit, or violating the terms of one, is a violation of the Unified Development Ordinance. The Floodplain Administrator can order work stopped immediately, and violating a stop-work order is a misdemeanor. Any other flood-ordinance violation is subject to Section 4.4's general civil penalty of $500 per violation, with each day of continued noncompliance treated as a separate offense.

Flood Zones FAQ

Do I need a permit to build in a flood zone in Alamance County?
Yes. Section 6.4.4 requires a Floodplain Development Permit from the Planning Director, acting as Floodplain Administrator, before any development activity begins in a mapped Special Flood Hazard Area, including grading, fill placement, or new construction.
What has to be in the permit application?
A certified plot plan showing the Special Flood Hazard Area boundary, flood zone designation, floodway or non-encroachment area boundary, and Base Flood Elevation where set, plus proposed elevation data for every structure's reference level tied to NAVD 1988, under Section 6.4.4.
Does the floodplain ordinance apply outside county limits?
It reaches the unincorporated county and the Extra-Territorial Jurisdiction the county shares with the Village of Alamance, under Section 6.4.1. Land inside Burlington, Graham, Mebane, or Elon is governed by that municipality's own code, not the county's UDO.
What happens if I build without the permit?
The Floodplain Administrator can issue a stop-work order, and ignoring it is a misdemeanor. Other violations of the flood provisions draw a $500 civil citation per day under Section 4.4's general enforcement schedule until the property is brought into compliance.

Sources & official references

Flood Elevation Requirements

Alamance County Flood Elevation and Freeboard RulesSome Restrictions

Alamance County requires new and substantially improved residential structures in Special Flood Hazard Areas to elevate the reference level, including any basement, no lower than the Regulatory Flood Protection Elevation. That elevation is the FEMA Base Flood Elevation plus two feet of freeboard, or two feet above the highest adjacent grade where no BFE has been set.

Key Facts

Freeboard
BFE plus 2 feet
No-BFE standard
2 feet above highest adjacent grade
Enforcing agency
Planning Department Floodplain Administrator
Permit required
Floodplain Development Permit before construction
Civil penalty
$500 per day per violation
Small accessory exemption
Under 150 sq ft or $3,000

New construction and substantial improvement of any residential structure, including manufactured homes, shall have the reference level, including basement, elevated no lower than the Regulatory Flood Protection Elevation. […] REGULATORY FLOOD PROTECTION ELEVATION: The Base Flood Elevation plus the Freeboard. In Special Flood Hazard Areas where Base Flood Elevations (BFEs) have been determined, this elevation shall be the BFE plus two feet ("freeboard"). In Special Flood Hazard Areas where no BFE has been established, this elevation shall be the at least two feet above the highest adjacent grade.

Full breakdown

The Alamance County Unified Development Ordinance, amended December 16, 2024, sets the county's elevation standard for flood-prone construction in Section 6.4.6, Development Specific Provisions for Flood Hazard Reduction. Under the Residential Construction provision, new construction and substantial improvement of any residential structure, including manufactured homes, must have its reference level, including any basement, elevated no lower than the Regulatory Flood Protection Elevation. Article 2's definitions section pins down that number: it is the FEMA Base Flood Elevation plus two feet of freeboard in Special Flood Hazard Areas where a BFE has been determined, or at least two feet above the highest adjacent grade where none has been set.

Non-residential structures in Zones A, AE, AH, AO and A99 may floodproof to the Regulatory Flood Protection Elevation instead of elevating, but a registered professional engineer or architect must certify the floodproofing and file that certification, an operational plan, and an inspection and maintenance plan with the Floodplain Administrator. Manufactured homes must have their reference level at or above the same elevation and be anchored to resist flotation and lateral movement; chassis raised more than 36 inches require an engineering certification. Small accessory structures, those with a footprint under 150 square feet or representing an investment of $3,000 or less, are excused from the elevation and floodproofing standards if they meet anchoring and low-damage-potential criteria.

Before any of this work begins, the owner must obtain a Floodplain Development Permit from the Planning Director, who serves as Floodplain Administrator, under Section 6.4.4, submitting a plot plan showing the Special Flood Hazard Area boundary and proposed reference-level elevations tied to NAVD 1988.

Violations & penalties

Building below the Regulatory Flood Protection Elevation without a Floodplain Development Permit is a violation of the UDO. The Floodplain Administrator can issue a stop-work order under Article 4; disobeying it is a Class 1 misdemeanor under G.S. § 160D-404. Any other violation not otherwise addressed draws a $500 civil citation per Section 4.4, with each day of continuing noncompliance treated as a separate offense subject to the fine.

Flood Elevation Requirements FAQ

How high above the base flood elevation must I build in Alamance County?
Your home's reference level, including any basement, must sit no lower than the Regulatory Flood Protection Elevation: the FEMA Base Flood Elevation plus two feet of freeboard under UDO Section 6.4.6. Where FEMA has not set a BFE, the county requires at least two feet above the highest adjacent grade instead.
Can I floodproof instead of elevating?
Only non-residential buildings in Zones A, AE, AH, AO and A99 may floodproof to the Regulatory Flood Protection Elevation in lieu of elevation, and only with certification from a registered professional engineer or architect filed with the Floodplain Administrator. Residential structures must be elevated; floodproofing is not an option for them.
Does my shed need to meet the elevation standard?
No. Section 6.4.6 excuses accessory structures under 150 square feet or valued at $3,000 or less from the elevation and floodproofing rules, provided they are unheated, not used for habitation, and anchored to resist floodwater flow. Larger accessory buildings must still meet the full standard.
Who administers Alamance County's flood elevation permit?
The Planning Director, acting as Floodplain Administrator, reviews and issues Floodplain Development Permits under Section 6.4.4 and makes onsite inspections as work proceeds. Applicants must submit a certified plot plan showing proposed elevations in relation to NAVD 1988 before starting work in a Special Flood Hazard Area.

Sources & official references